Underlit structure two days before event
A practice run the evening before the first event day
Lower portion of the landing starts to build with steel decking set onto pipes rolled to specific radii
Base level to +12.5m starts to build on top of field cover
Day 3 - Evening
Landing slope nears completion
Day 5
Silvertanium insulation installed directly onto steel decking with white Enka-drain laid over the top
In-run - About half decked
Looking down from Start Gate level
Slopes completed and covered and stair steps going in
The unbelievable skill and perseverance of this team of guys & girls made this all happen - Best ever!
Structure completed and ready for banners & snow
Banners rigged
Snow being made on the landing. The first two of 52 tanker trucks
Snow being groomed one day before practice started
Showtime!